If it takes 4 workers 21 hours to paint how many hours will it take 12 workers?

Respuesta :

m11233982
m11233982 m11233982
  • 12-09-2022

Answer:

63 hours

Step-by-step explanation:

4 workers = 21 hours

12 workers = g

[tex] \frac{21}{4} \times 12 \\ = 63hours[/tex]

Answer Link

Otras preguntas

220 is 95.3% of what number?
What is the meaning of the Greek root port as it is used in the word comports?
Someone help please ASAP. In∆ABC, m a) How are the measures of m b) Solve for x:
Which ratio does not belong with the other three, explain your reasoning. 4/10, 2/5, 3/5, 6/15
name at least two differences between the people in shakespeare's time-period and people today?
1 times x to the 1st power
Which part of the earth system interacts with solar flares? A. lithosphere B. hydrosphere C. atmosphere D. magnetosphere PLZZZZZZZZZZZZZZZZZZZZZZ HELLLLLLLL
Wayne has a recipe on 3 inch by 5 inch index card that he wants to enlarge to 15 inches long. how wide will the enlargements be?
Most investment returns in the U.S. are currently taxed at a 15% rate. Therefore, investors lose 15% of their returns to pay the cost of taxes. If the governmen
What is equivalent to 9-4